homepage - case studies - case study

Gas to Air

Client -  Automotive Part Casting Manufacturer, Kentucky, USA

 

Project – Aluminium Furnace Air Pre-Heater

 

As part of its energy review this global Multi national sought a means by which it could reduce its aluminium furnace running costs. After a period of technical consultation an Energy Spectrum GA 330 Gas to Air smooth pipe heat exchanger was selected for the installation.

 

The original business case was approved on the basis of a $100K per annum saving against a total estimated project costs of $168K. The installation  was successfully completed in March 2006 by local contractors operating to an Energy Spectrum  outline design.

  

The smooth pipe GA exchanger offers many benefits in this high particulate exhaust environment which include –

 

  • Low fouling susceptibility - due to smooth Non finned design
  • Ease of maintenance – pipes can be simply removed for cleaning (see illustration)
  • High reliability – through multiple redundancy design as each pipe operates independently so that a single pipe failure (in itself a rare event) will not incapacitate the unit

The overall installation design needed to be failsafe such that production would not be affected in the event the recovery unit needed to be switched off.. To address this challenge Energy Spectrum engineers specified a solution which allowed the unit to be simply by-passed for routine maintenance events using an innovative cost effective approach that avoided the need for costly exhaust diversion valves.

 

A further challenge was the very small available space in the proximity of the furnace heat source. Energy Spectrum engineers addressed this through a design that accommodates the entire recovery unit installation outside of the production facility as seen in the illustration.

 

In the event operational measurement against the pre-installation baseline indicated an annual saving in the region of $150K a figure 50% in excess of the original project target. This excellent result delivered a total payback period for the project of 13 months. Based on the success the client has now placed an order for 2 more exchangers.

 

 

welcome to Energy Spectrumwelcome to Energy Spectrum
website by nexus creative. all content copyright 2007 Energy Spectrum